openIssues identified in Product-UEM 6.2.0 testing process
Added by Thilina Sandaruwan 12 months ago. Updated 3 months ago.
Status:
New
Priority:
Critical
Assignee:
-
Start date:
13/12/2022
Due date:
26/08/2024 (about 10 months late)
% Done:
11%
Estimated time:
(Total: 0:00 h)
Description
Description
During the 6.2.0 testing process, both new and existing issues were identified. This parent ticket will be used to track and manage these issues effectively. The main purpose is to reduce the testing time for these identified issues in the next release.
Updated by Thilina Sandaruwan 12 months ago
- Subject changed from Issues identified in 6.2.0 testing process to Issues identified in Product-UEM 6.2.0 testing process
Updated by Lasantha Dharmakeerthi 11 months ago
- Project changed from product-uem 6.2.0 GA to product-uem 6.3.0 GA